The works are designed to renovate section from river mouth up 1.8 kilometer lenght to central part making  more attractive face of city.

The 1.8 km quay wall extension is being built using a double sheet pile system of  HEOSCH and angles.

  • 1.711 t Larssen 703 K double,  lenght - 10,500 – 7,000 m
  • 0,104 km,  Omega 12

The quay wall is anchored using  injection TITAN anchors. Instaled using „Jet grouting“ method.

  • 7,470 km, TITAN 40/16
  • 1,246 km, TITAN 52/26

Equipment used for  instaling sheet piles and anchors:

  • Müller MS – 7 HFB with  MS- A 285 5 V
  • Müller MS – 10 HFV with  MS- A 285 5 V
  • Casagrande drilling equipment.